| 1 |
 |
January 9: First Tube
Our first order of business was to make the tubes for the booster.
We had a big turnout and there was lots of excitement about getting started.
|
| 2 |
 |
January 16: Another Approach
In an attempt to remedy the problems with our first tube,
we made a shorter sample tube.
|
| 3 |
 |
January 23: Second Tube
We decided to make the second attempt at a booster tube,
this time using what we'd learned in the process.
We produced our first usable tube!
|
| 4 |
 |
January 30: Yet More Tubes
Now that we had the tube technique down, we proceded to make more tubes.
We created the second booster airframe tube,
and a fiberglass-only section of booster airframe.
|
| 5 |
 |
February 20: Final Tubes
Now that we had the airframe tubes done,
we just had to build a few smaller tubes for the interstage.
|
| 6 |
 |
February 27: First Construction
Three groups worked on different parts: making the final sustainer socket tube,
cutting the tubes we'd already made to length and building the interstage.
|
| 7 |
 |
April 2: Making Parts
We worked on components, including the nose cone mold,
interstage pieces, couplers and ARLISS cansat carriers.
|
| 8 |
 |
April 10: Nose Cone & Interstages
The main work at this session was making the mold for the custom nose cone.
|
| 9 |
 |
April 23: Making Molded Parts
We made a the first nose cone and interstage shroud from the two molds.
|
| 10 |
 |
May 7: Second Molding
We made the second nose cone and interstage parts from the molds and started
working on the sustainer airframe.
|
| 11 |
 |
May 14: Interstage & Sustainer
We fitted the interstage shrouds to the bodies,
started bonding the first sustainer fins
and started building the forward end of the sustainers.
|
| 12 |
 |
May 21: Airframe Continuation
We cut the booster tubes to final length,
fitted the interstage couplers,
started reinforcement of the sustainer fins
and continued building the sustainers.
|
| 13 |
 |
May 22: Sustainer Completion
We cut the rest of the sustainer parts out and drilled the holes for bolting
and continued tip-to-tip reinforcement of the sustainer fins.
|
| 14 |
 |
May 25: Booster Fins
we cut the booster fins from the honeycomb plate and installed the first one on each booster.
Also, we completed the last tip-to-tip reinforcement of the sustainers.
|
| 15 |
 |
May 28: Airframe Complete
We reinforced the booster fins tip-to-tip,
completed the construction of the interstages
and finished the cansat carrier.
|
| 16 |
 |
June 6 & 7: Electronics Assembly
At Steve's shop in Petaluma,
The booster and sustainer electronics were assembled and fitted
and antennas were built.
|
| 17 |
 |
June 11 & 12: A Final Flurry
At the final session before Mudroc, we got the airframe complete.
|
| 18 |
 |
July 2: Some Finish Work
we finished a few remaining tasks on the aiframe,
getting it ready for painting.
|
| 19 |
 |
July 16: Test Fit Recovery
we finished a few remaining tasks on the sustainer and test fit the recovery system.
Airframe #1 is ready to fly at Aeronaut!
|